Understand the idea
Being 'in control' (stable, predictable variation) and being 'capable' (able to meet the customer's requirements) are two different questions. A process can be perfectly stable and still produce plenty of out-of-spec parts if its natural spread is simply too wide for the tolerance window it needs to fit inside.
Capability indices answer the second question directly by comparing the width of the specification window to the width of the process's natural variation. Cp compares the two widths assuming the process is perfectly centered; Cpk also accounts for how far off-center the process actually is, so a process can have a good Cp but a poor Cpk if it is running close to one spec limit. Pp and Ppk make the same comparisons using the spread of all the data together, including drift between batches, instead of the short-term spread within batches.
A commonly used rule of thumb treats Cpk of 1.33 or higher as capable and 1.0 as marginal, but a low Cpk always has two possible fixes: reduce the process's variation (make it more consistent), or re-center it (shift the average closer to the middle of the specification window), and it is worth checking which one is the actual problem before assuming the process needs to be made less variable.
Process capability is how well a stable process can meet its specification limits, and a capability index puts that into a single number.
Practitioner explanation
Cp = (USL - LSL) / (6*sigma) assumes the process is centered and is a POTENTIAL capability measure; Cpk = min[(USL - mu)/(3*sigma), (mu - LSL)/(3*sigma)] accounts for off-centering and is always <= Cp, with the gap between them diagnosing how much of any capability shortfall is a centering problem versus a pure variation problem.
Cp/Cpk use sigma estimated WITHIN-subgroup (short-term, excluding shift-to-shift or day-to-day variation); Pp/Ppk use the OVERALL sample standard deviation (long-term, including that between-subgroup variation) and are usually (not always) below Cp/Cpk for the same data; when the moving-range or within-subgroup estimate happens to exceed the overall SD, Pp can come out above Cp. Reporting Cpk from an unstable process (one that failed its own control chart) is a well-documented misuse: Cpk assumes a predictable, single-distribution process, and a Cpk computed on out-of-control data describes a moving target, not a capability.
KernelStats' Process Capability (Cp / Cpk / Pp / Ppk) engine reports Cp, Cpk, Pp and Ppk together on one card specifically so the within/overall and centered/off-center distinctions are all visible at once, flags parts-per-million estimates for both the observed and the expected-under-normality tails, and the card's guidance notes that Cpk is only meaningful once the underlying control chart shows the process is stable.
When to use it
Consider it when
Once a control chart has shown the process is stable (in statistical control) and you want to quantify whether it can meet a specification.
Use caution when
Do not compute or report Cpk on data from a process shown to be out of control: an unstable process has no single, well-defined distribution for the index to describe.
Formulas and symbols
Process capability index Cp
USL/LSL are the upper/lower specification limits; sigma is the process's within-subgroup standard deviation.
Process capability index Cpk
mu is the process mean; Cpk penalizes a process that is not centered within its specification window.
Alternatives
- Non-normal Capability (Percentile Method). The measurement is clearly non-normal (skewed, bounded); Cp/Cpk assume normality and a non-normal capability method (percentile-based, or a fitted distribution) avoids a misleading index.
Common misconceptions
Misconception
A Cpk computed from any batch of data tells you the process is capable.
Correction
Cpk is only meaningful for a STABLE process (one that has passed its own control chart). Computing Cpk on data from an out-of-control process describes a moving target and the number does not mean what a capability index is supposed to mean.
Read more: Misconception: Cpk is meaningful even for a process that is not in statistical control
References
- NIST/SEMATECH e-Handbook of Statistical Methods, §6.1.6 What is Process Capability?, NIST/SEMATECH (2012), §6.1.6.