Understand the idea
Control limits come from WATCHING the process: they are computed from the process's own historical spread, and they answer 'has something changed compared to how this process usually behaves?'. Specification limits come from OUTSIDE the process entirely (an engineering drawing, a customer contract) and they answer 'is this particular part good enough to ship?'.
A process can be perfectly stable (well inside its own control limits, behaving exactly as it always has) while still producing a steady stream of parts outside the specification limits, if the process's natural variation is simply too wide, or badly centered, for the tolerance window the customer requires. Being 'in control' and being 'capable' are different claims, and mixing up the two limits hides that difference.
The confusion runs both ways and both are serious errors: plotting specification limits on a control chart (and reacting to every point near the spec line as if it were a process shift) is one version; treating being within control limits as proof that every part meets specification is the other.
Specification limits are written USL (upper) and LSL (lower), and they come from the customer or the design, not from the process data. Comparing the process spread with the specification limits is what process capability measures, which is a separate question from whether the process is in control.
Practitioner explanation
Control limits are set at the process's own center line +/- 3*sigma_hat, with sigma_hat estimated from IN-CONTROL process data (via R-bar/d2, S-bar/c4, or a moving-range estimator, depending on chart type); specification limits are set by engineering or contractual requirement and have no necessary numerical relationship to the process's actual spread at all: they can sit inside, outside, or symmetrically or asymmetrically around the control limits.
Capability indices (Cp, Cpk) exist precisely to compare these two DIFFERENT quantities against each other (specification width against process spread), which is why Cp/Cpk are undefined or meaningless without both a stable process (established via the control chart) and a stated specification (which the control chart itself never uses).
KernelStats keeps control limits and specification limits as visually and numerically distinct inputs throughout: control charts (the X-bar R chart, the I-MR chart, and the attributes charts) never take a specification limit as an input, and Process Capability (Cp / Cpk / Pp / Ppk) requires the specification limits to be entered separately from, and in addition to, the process data used to estimate sigma.
Worked example
Scenario
A machined part has a specification of 10.0 mm +/- 0.1 mm. The process's control chart shows it stable, with control limits at 9.85 mm and 10.15 mm based on its own historical variation.
Result
The process is in statistical control, but Cpk comes out at 0.67 (below the conventional capable threshold of 1.33).
Interpretation
The process is behaving consistently with itself (in control) but its natural spread is simply too wide relative to the tight +/- 0.1 mm specification (not capable). Fixing this requires reducing the process's own variation or re-centering it, not merely confirming it remains 'in control' by its own historical standard.
Common misconceptions
Misconception
If a process is within its control limits, every part it produces meets specification.
Correction
Control limits describe the process's OWN natural variation; specification limits describe what is acceptable to the customer. A stable, in-control process can still have natural variation wide enough, or centered far enough off-target, to routinely produce parts outside specification; that is exactly what a low Cpk describes.
References
- NIST/SEMATECH e-Handbook of Statistical Methods, §6.1.6 What is Process Capability?, NIST/SEMATECH (2012), §6.1.6.